Promenade in Herceg Novi Reconstructed Until New Year's Eve

By , 19 Dec 2018, 04:49 AM Lifestyle
Promenade in Herceg Novi Reconstructed Until New Year's Eve Copyrights: Radio Jadran Photo

Share this:

18 December 2018 - The paving of the part of the promenade in Herceg Novi from the restaurant "Galeb" to the restaurant "Mimoza" is almost finished. There are still a hundred more segmental paver boards along the edge, and before that, another one will be installed afterward, said Boro Lučić, director of the Agency for Construction and Development of Herceg Novi.

"We finished the lighting. Procurement is in progress, and we have already set up decorative lighting, benches and waste bins. By the end of next week, a complete promenade will be completed. We have completed all construction work, and the rest is 150 of these boards to be procured. That is what made us happy, so we ordered it, and it should come in the next 2-3 days," said Lučić.

The contract on the installation of mobilier and electrical installations, worth 15.000 EUR was agreed between Municipality of Herceg Novi and the company Niveda DOO, whose workers have already been engaged in the pavement of this route.

Promenade1812 1

Lučić said that the mobilier for the promenade would be delivered during the next week. As installation does not need more than a couple of days, the whole reconstruction of the promenade will be arranged until New Year. Herceg Novi Municipality is obliged to pay an advance payment of 20% of the agreed price to the contractor and the rest after the completion of the works.

Unless there are any unforeseen circumstances, the contractor is obliged to complete the work within 20 calendar days from the day the advance payment is made. The warranty period for works carried out is two years.

This 365 meters long part of the "Pet Danica" promenade started at the end of November. However, the reconstruction began in October 2015. Due to many administrative obstacles and projections, the works were interrupted several times, and the value of the entire project from the originally planned 360 thousand EUR reached almost 400 EUR.

The contractor was also changed, so the contract was terminated with the first, Bar Đokić group, while Niveda DOO from Herceg Novi was selected as the new performer.

Source: Radio Jadran