26 November 2018 - Construction works on the bridge Moračica, the most demanding and complex facility on the priority section of the Bar-Boljare motorway, are being performed in line with the planned schedule.

There are around 150 workers on the construction site being engaged every single day.

China’s CRBC Company assessed the construction of the Moračica Bridge spanning structure will require around 30,000 cubic meters of concrete and over 5,000 tons of metal framework.

The most complex facility on the first section of the highway Bar-Boljari will be finished by April 2019.

“Because of its height, range, use of formwork, the bridge connects in the air. We are going to do console construction of the main carrier. We are going to lay concrete on both sides of pillars, simultaneously. Everything has to be balanced,” said Ivana Maksimović earlier this year, from the Department of technical preparation in Section I.

She also added that the bridge has been designed in such a way that it meets all standards and noted that if the speed of the wind reaches the limit that the company will stop the works. 

Apart from this one, 19 more bridges will be built at the 41-kilometer long section.

Total Montenegro News wrote about the start of the works here and you can read more about Moračica bridge recent works here.

Remax Property of the Week

Property of the week.png

Editorial

Interview of the week

Photo of the Week

Photo galleries and videos